Track Progress

TRACK LAYING PROGRESS – End February 2011

TRACK LAYING PROGRESS – End February 2011

The final of 150 meters of track was laid on Thursday 3 March 2011. A grand total of 22.437 kilometres of slab track has been laid, using an overall 16 200m³ of concrete.     Select a thumbnail below to...

Read More

TRACK LAYING PROGRESS – End January 2011

TRACK LAYING PROGRESS – End January 2011

A total of just under 150 kilometres of track needs to be laid for the Gautrain route. By end January 97% of the track will be laid. Select a thumbnail below to...

Read More

TRACK LAYING PROGRESS – MID NOVEMBER 2010

TRACK LAYING PROGRESS – MID NOVEMBER 2010

A total of just under 150 kilometres of track needs to be laid for the Gautrain route. By mid November 89% of the track will be laid. Select a thumbnail below to...

Read More

TRACK LAYING PROGRESS – END SEPTEMBER 2010

TRACK LAYING PROGRESS – END SEPTEMBER 2010

A total of just under 150 kilometres of track needs to be laid for the Gautrain route. At the end of September 82% of the track was laid. Select a thumbnail below to...

Read More

TRACK LAYING PROGRESS – END AUGUST 2010

TRACK LAYING PROGRESS – END AUGUST 2010

A total of just under 150 kilometres of track needs to be laid for the Gautrain route. At the end of August 75% of the track was laid. Select a thumbnail below to...

Read More

TRACK LAYING PROGRESS – END JULY 2010

TRACK LAYING PROGRESS – END JULY 2010

Construction of the viaduct that crosses the N1 and the John Vorster Interchange was completed during June 2010. Erection of catenary masts over this structure has been completed and tracklaying operations are also in progress A total of just under 150 kilometres of track needs to be laid for the Gautrain route. At the end of July 66% of the track was laid. Select a thumbnail below to enlarge ...

Read More